MT Barker South 275/66kV Substation
The project required the complete design of the new 275/66kV substation, this included civil, structural earthworks and electrical design. The secondary works included all protection SCADA configuration (Logica RTU�s) and on site testing.
The project involved:
- 1 x 275/66kV 225MVA Transformer;
- 2 x 275kV Line;
- 2 x 275kV busbar;
- 2 x 275kV Diameters;